Sewer Projects

Included below are the anticipated sewer line work areas for the week of 7/26/2021, weather permitting. 

 

Old Conemaugh Borough (Liberoni, Contract 2018-01)

Open cut lateral installation and main line rehabilitation will be continuing on Ridge Ave. as well as lateral installation on Church Ave.  Expect road closures on a block by block basis.  Mink Alley will be open to through traffic to Church Ave. or Ridge Ave.

 

Old Conemaugh Borough (Snyder, Contract 2018-02)

Asphalt base repair, concrete, and grass restoration will be occurring throughout the project area.  Expect minimal road closures throughout this process. 

 

Fairfield Ave. (Terra Works, Contract 2018-03)

Terra Works will be continuing asphalt base repair along Fairfield Ave. in the lateral ditch line crossings between J St. and Strayer St.  A storm manhole will also be installed near the railroad underpass.  Concrete work will also be taking place along Fairfield Ave. Expect one lane closures with flagging to take place.

 

Fairfield Ave. (Terra Works, JRA Contract 2018-INT-01)

Please refer to Contract 2018-03 anticipated work description.

 

Kernville (Snyder, Contract 2017-08)

Snyder is anticipating lining laterals on Franklin St. near the Hospital on Thursday & Friday.   

 

Clinton St. (Snyder, JRA Contract 2020-INT-1)

Snyder will have a crew on Clinton St. installing manholes  within an area controlled by 24/7 traffic lights.

 

Central Business District (Snyder, Contract 2019-27)

Camera work will be taking place throughout the week within the base bid areas which include Main St. and surrounding streets.  Camera work may also be taking place in the Alternate 1 areas which is near Vine St. and Napoleon St.  Expect minimal traffic disruptions throughout camera work.

Affected Area: 

Google Map

Google Map

Google Map

Google Map

Status Update (chronological): 

Sewer work for the week of July 26th, 2021