Anticipated Sewer Work Week of September 26, 2022

Included below are the anticipated sewer line work areas for the week of 9/26/2022, weather permitting. 

 

Greater Johnstown Water Authority

Old Conemaugh Borough (Liberoni, Contract 2018-01)

No work is anticipated.

 

Central Business District (Snyder, Contract 2019-27)

  • A crew will be working on open cut laterals throughout the project area
  • A concrete crew will be onsite throughout the project area working on final restoration
  • A CIPP lateral lining crew will be onsite working on Washington St. to line laterals
  • A manhole rehabilitation crew will also be onsite working throughout the project area
  • Expect one lane closures or minimal traffic disruptions throughout these processes

 

Miscellaneous Sanitary Sewer Project (Snyder, Contract 2022-01S)

An open cut lateral crew will be working on Strayer St. installing laterals. Expect temporary traffic signals and one lane closures along Strayer St.  Snyder will also be continuing open cut main line installation along Cooper Ave. near Stutzman St. Expect lane closures and/or traffic adjustments along Cooper Ave.