Anticipated Sewer Work Week of November 21, 2022

Included below are the anticipated sewer line work areas for the week of 11/21/2022 Monday through Wednesday, weather permitting. 

 

Greater Johnstown Water Authority

Central Business District (Snyder, Contract 2019-27)

  • A crew will be onsite Tuesday and Wednesday working on various punch list items throughout the work area
  • A CIPP lateral lining crew will be working in CBD finishing up outstanding lateral work
  • A manhole rehabilitation crew will also be in town working throughout the week in various locations
  • Expect minimal traffic disruptions throughout these processes

 

Miscellaneous Sanitary Sewer Project (Snyder, Contract 2022-01S)

  • Snyder will have a crew installing a lateral above Hagen St. on Monday
  • A paving crew will be finalizing asphalt patching on Strayer St. on Monday before finishing base repairs on Cooper Ave. Tuesday and Wednesday
  • An open cut crew will be working on main line installation along Branch St. just off of Roosevelt Blvd.
  • A concrete crew will be on site working on sidewalk restoration along Cooper Ave. 
  • Expect lane closures and/or traffic adjustments along Cooper Ave.